Bangor International Airport will close its runway for several multi-day stretches in April, May and June to finish rebuilding the aging landing strip.
Last year the airport started rebuilding the runway, which it said “had reached the end of its useful life.”
After the planned closures, listed below, the runway will be shortened for the remainder of the project, but the airport does not anticipate additional disruptions to members of the public who are traveling.
16-Hour Closures
7 p.m. Tuesday, April 22 – 11 a.m. Wednesday, April 23
7 p.m. Tuesday, Sept. 9 – 11 a.m. Wednesday, Sept. 10
55-Hour Closures
8 a.m. Monday, April 28 – 3 p.m. Wednesday, April 30
8 a.m. Monday, May 5 – 3 p.m. Wednesday, May 7
8 a.m. Monday, May 12 – 3 p.m. Wednesday, May 14
8 a.m. Monday, May 19 – 3 p.m. Wednesday, May 21
8 a.m. Monday, June 2 – 3 p.m. Wednesday, June 4
8 a.m. Monday, June 9 – 3 p.m. Wednesday, June 11
8 a.m. Monday, June 16 – 3 p.m. Wednesday, June 18